Project Overview:
The main construction content of the advanced section is the foundation pit of the water inlet shaft of Jiuquyang Port and the lining of the lower part of the shaft, as well as the temporary works required to complete the above projects. Among them, the lining diameter of the Jiuquyang Port water inlet shaft is 23m, the depth below the surface is 64m, the excavation diameter is about 27m, and the ground connection wall is about 74m deep.
Automated monitoring equipment
Device name:Inclino-Robot IRA
Model:IRA-100
Quantity:1set
Hole Depth:67m
Starting Method:Starting from the orifice
Life Cycle:2023.05-2024.03
Installation pictures
Data Display
Monitoring data from the same measuring point in different time periods